Country-Plan Projects and Tenders |
|
6553 Subject |
195 مليون دولار قيمة التمويل الاجنبي للمطار الجديد وعدد 7 عروض تحت الدراسة 7 offers to execute terminal building No. 3 at Cairo Airport still under evaluation. |
| Date Published | Sunday, July 18, 2004 |
| Source Name | Gomhouria |
| Location Name | Cairo |
| Description | According to Eng. Ibrahim Mannaa, Chairman of the Holding Co. for Airports, earlier submitted 7 offers for the construction of Cairo Airport terminal building No.3 are (still) under evaluation according to precise criteria in full secrecy and absolute transparency. He indicated that evaluation results would be presented to the World Bank, financing the project under $ 295 million loan. Job is projected for completion in about 32 months. The new building will have a capacity to handle 11 million passengers / year. |
| Sectors Section |
Beneficiary Sectors - Construction Projects Integrated works Airports |