6993 Subject |
سيمنز من المانيا وجنرال اليكتريك من امريكا ومتسوبيشي من اليابان في قائمة الشركات لمناقصة مجموعة التوليد للكهرباء للتوسعات في محطة طلخا 750 ميجا وات Siemens of Germany, General Electric of the US & Mitsubishi of Japan seem to be front runners for the gas turbines package of Talkha 750 MW combined cycle power station project. |
| Date Published | Wednesday, September 15, 2004 |
| Source Name | Al Alam Al Yom |
| Location Name | Dakahliya |
| Description | Siemens of Germany, General Electric of the US & Mitsubishi of Japan seem to be front runners for the $ 100 million gas turbines package of Talkha 750 MW combined cycle power station project. Client is East Delta Electricity Production Co. Overall project costs are put at L.E. 1.84 billion. |
| Sectors Section |
Beneficiary Sectors - Electromechanical Works Electromechanical Works - Energy Generation |